Wednesday, 6 June 2018

Contaminated Hinkley mud to hit beaches at Penarth and Barry

The regulator "Natural Resources Wales" announced 6th June that conditions on the license are now complete for dumping 300 000 tonnes of contaminated sludge in the Estuary off Penarth Head.

The license but not the monitoring is at
Further questions may be put to NRW via marinelicensing@naturalresourceswales.gov.uk

This is Barry&Vale FoE's new publicity leaflet on the issues.

** Why call it "Hinkley's mud".  It's not 'nuclear sludge' from inside the reactor, not mud from the nuclear operations, but estuary mud that picked up radioactive elements from the plant's liquid discharges (with microparticle 'dirt'). While these discharges were licensed at the time, limits were not necessarily enforced and current permits are stricter. What's in the mud is largely unknown; the few samples taken of 'historical' mud in 2009 at a few metres below the seabed show elevated levels of uranium and radium.  Those samples have been lost so cannot be re-tested.  There may be plutonium, since its production was a major purpose of Hinkley Point A station, but this was secret.

Tuesday, 5 June 2018

Metro-trams unacceptable on Penarth Rd thru Grangetown

Battery-driven trams welcome - but not on-street through Grangetown
We welcome the choice of KeolisAmey’s battery-driven trams for the Cardiff region metro, says Max Wallis of Friends of the Earth Barry&Vale.  While they can switch to overhead power lines for some stages, on-street overhead lines are avoided, likewise on the spur to Penarth in Cardiff.
We call on the company to drop the plan of Transport for Wales to route the Penarth trams on-street through Grangetown. 
Reconstruction at Grangetown Station to get the trams between Penarth Road and the overhead rail line would be substantial. 
The trams will be caught up in the traffic jams; journey times Penarth to Cardiff would be much longer than the present 11 minutes. 

Unless battery-trams are allowed to run on the ordinary rail lines, through to Central and Queen St stations, FOE doesn’t want them on the Penarth line.  Let us keep diesel trains as on the Barry Island and Vale of Glamorgan lines, with modern rolling stock too.  We regret that those services are not to be electrified, but let’s avoid Cardiff’s hotch-potch with on-street battery-trams.

Five-Mile-Lane archaeology at 5th June Meeting

Guest speaker on the Archaeology discoveries and destruction at Five-Mile-Lane
Update of Issues:
1/ Global and Local – Extreme Thunderstorms and extensive rainfall leads to localised and widespread flooding in many countries - Global Storming. Record heat temperatures continue to be monitored worldwide, 45C in India, people dying of heat in Pakistan, 50C+ in Middle East, warmest May on record in Wales, Volcanic activity grows from Guatemala to Hawaii and Indonesia - Global Warming. Good news locally- Cleaner waters and Blue Flags. Bird life range and variety slowly increasing.
2/ Local and Global – Wylfa Nuclear Power Station gets the go ahead. Hitachi gets the nod from Westminster. Will the Chinese also get the nod at Hinkley Point? Hinkley's Nuclear Mud – We hardly need contaminated material dredged from Hinkley, to be spread over our improving coast. In a debate on May 23rd , the Minister gave the go-ahead, ignoring evidence, petitions and demonstrations. Max has produced Leaflets for distribution. The fight continues.
3/ Local - 5 Mile Lane – Ancient Woodlands and Archaeology issues and consultation begins on M4/A48 link road proposals. Archaeology Group may wish to speak to the meeting.
4/ Local – National – Swansea Lagoon and Tidal Power – it looks as if the Government are sending this Welsh project the same way as our electrified railways. It seems that Wales is not value for money when it comes to large environmentally sound investments. Doubts about the way the Tidal Lagoon project has gone ahead, including concerns given to FoE by residents across the Severn.
5/ Local and Global - DIAG and the Incinerator – Ten years on. DIAG has 8 solid objectives in their continued campaign. EIA still awaited. Further concerns for Waterfront residents have arisen. Housing Contracts – Residents have to accept oversight of polluted areas as in the Graving Dock. This was filled with polluted material from the initial Waterfront development and cannot now be built on.-
6/ We have a blog where you can acess information and contribute to campaigns/debates - https://barryvalefriendsoftheearth.blogspot.co.uk

7/ AOB:   next meeting, Tuesday July 3rd
Keith Stockdale,
Barry/Vale FoE Coordinator

Friday, 25 May 2018

Hinkley Mud debate report and video

Neil McEvoy AM speaking in the Senedd debate, 23 May 2018

Neil was the first AM to raise the issue in the media and sat on the Petitions Committee giving consideration to the massively supported Petition calling for the dumping license to be cancelled.

Report of the Senedd debate in Penarth Daily News here

On 6th June, NRW announced they have updated the license and cleared the final condition on monitoring.
The license but not the monitoring is at

Further questions may be put to marinelicensing@naturalresourceswales.gov.uk

Thursday, 24 May 2018

Hinkley Mud dumping -Senedd debate 23 May

The one- hour debate at the Senedd on Wednesday showed the Welsh authorities wanted to close down the issue, despite the Petitions Committee report being interim, as questions were unanswered.
                           Anne Greagsby (Barry&Vale FoE) with Welsh Anti-Nuclear Alliance's poster and 
                           new banner behind, on the Senedd steps prior to the debate 

    Various Assembly members including the Vale’s Jane Hutt and Cardiff’s Gareth Bennett voiced the concerns of constituents over ‘nuclear sludge’ being dumped on Wales, arguing that further testing of deeper samples is needed for public assurance.  Jane Hutt supported Committee member Mike Hedges’ request for review by independent academics, whom people trust more than official agencies.
   Committee chair David Rowlands biased the debate by quoting the NRW statement on radioactive substances being “no greater concentration at depth”, yet did not mention the CEFAS** data that showed the contrary - up to three times the uranium and radium at a few metres depth – as agreed by CEFAS in a new letter (30 April).  He said the Committee had written to NRW in January asking for deeper samples.  The company refused saying “not radioactive” but neither Rowlands nor the Committee appeared to challenge this obviously false statement.
   David Melding (of Penarth) regretted that the company did not respond to the request for deep samples, saying he’s open for new evidence if it’s brought forward.  Cardiff AM Neil McEvoy said the data do show radioactivity is higher at depths of material which is to be excavated, such that radioactive dose could exceed the “de minimis” level of international standards for dumping at sea.  He wanted the license suspended till further testing is done.
   Simon Thomas supported a pause for more testing, while claiming he’d ”not seen any evidence that the material is radioactive”.  How strange that Plaid’s environment spokesperson does not understand that the measured gamma radiation is, actually, radioactivity!  He spoke also about dumping material in the Welsh Severn Estuary avoids landfill tax, which would deliver £27 million if landfilled in Wales (300 000tonnes @£88.95 per tonne)
   Caroline Jones said emotionally, the south Wales coast is special, we need every action to protect our ecology.  Committee member Janet Finch-Saunders was bothered that this big company  refused to undertake deep sampling.  She said the chemical contaminants are above CEFAS Action Level-1, described by them as a “small breach”.  A breach by any name!   She proposed the Welsh government use its Marine Act powers until the chemicals’ impact on the Severn marine conservation area had been assessed.
   The Minister Hannah Blythyn in reply read a prepared speech, taking nothing on board and claiming the committee had “carried out a thorough review”.   It said the CEFAS assessment was “fully in line within international standards”, showing “no radiological risk to people and the environment”.  In fact, CEFAS ignored the international requirement introduced in 2015 for assessing radiological impact on ecosystems.  They left the chemical impacts to NRW, who had done nothing.  Carwyn’s Government again not listening.


 ** CEFAS = Centre for Environment, Fisheries and Aquaculture Science, an executive agency of the Department for Environment (England).
Friends of the Earth Barry&Vale comment: 
we were encouraged by the support of so many AMs, responding to petitions totalling around 100 000.   Our evidence was taken up by the committee, but in the end the Committee chair ignored it, choosing not to report the 3-fold increased radioactivity at depth that proved the case for further deep sampling.  He also choose not to report that NRW had not carried out an assessment of the added toxic chemicals dumped in the Severn Estuary.  We think to take these breaches of European law to the Commission (pre-Brexit!).  

Friday, 20 April 2018

Hinkley radioactive mud: brief to Senedd Petitions Committee 17 April 2018

Petition P-05-785 Suspend Marine License 12/45/ML
Comments on NRW response of 27 March, from Friends of the Earth, Barry&Vale. 
We formulated a briefing earlier, on the basis of our FoI request to NRW for all documents relating to this license application held by them.  We are therefore confident that we have viewed most of the background material.  We enclose that briefing for use of the Committee and add the following re the latest NRW letter to you.
Contrary to NRW we see the Sampling of sediment as not primarily for public reassurance, as stated, but to meet licensing requirements.  Sampling at depth, as the Committee requested, is likewise needed to meet licensing requirements: Licence Condition 9.5 requires satisfying NRW that the material is suitable for deposit at the site.
1. The applicant’s refusal of deep samples is unacceptable.  
It depends on NRW’s statement “there is no scientific basis for any additional sampling” which is false.  The Committee were wrongly told earlier there is no scientific evidence of higher radioactivity in deeper sediments in the Hinkley Point area. (as on the NRW website).  The evidence is clear in the 2009 data for U238 and Radium, as in the reduced Table below: the numbers show 3 out of the 5 samples were significantly higher at depth (up to 3x for Radium - Ra). 

2. No specialist/expert assessment by Welsh authorities
   "we consulted Public Health Wales and NRW’s own internal expert in relation to the dose analysis results" 
 No report is provided (no transparency); this sentence refers only to the radiological dose, not to the chemical constituents.

3. The de minimis criteria are for disposal at sea. 
The IAEA-TECDOC-1375 defines this to include well-mixed near-coastal waters
“The disposal is assumed to take place a few kilometres off the coast so the actual shape of the coastline does not influence the dispersion significantly.”
The Severn Estuary site is not “sea” , but estuarial water with distinct circulation and ecology, which does not satisfy the IAEA criterion. 

4. Disposal in the Estuary requires information on dispersal of the radioactivity and use of a habits survey to calculate collective dose.  Cefas use a habits survey from the Cumbrian shore for sea-food consumption and beach-combers/recreation. The Severn Estuary is very different and sea-land transfer potentially much stronger.

5. the NRW letter does not cover the chemical contaminants, though they are required to assess their impacts.  Their Website says: Chemical contaminants were assessed against Cefas Action Levels[2]   UK guidelines to assess dredged material and its suitability for disposal to sea.   Several metal and organic contaminants were measured as above Action Level-1, yet no assessment has been made by NRW.

6. CEFAS say Dredged material with contaminant levels between Action Levels 1 and 2 requires further consideration and testing before a decision can be made.
The documents show no further assessment – which of course must be against the characteristics of the dump site and conducted under criteria relevant to it.  For this European “Special Area of Conservation”, criteria from biodiversity/Habitat legislation obviously come in, but none have been considered.  The end-fate of the contaminants must also enter, requiring consideration of the cited studies on deposition on the estuarial mud flats and transfer to marine life and to the land.

7. The Licence conditions 9.5, 9.11 require that the sediments are suitable for deposit and that dispersal via re-suspension should be avoided.  It’s not shown how this could be done in practice.  Discharge is planned by dropping from the barge, but the only way to ensure “deposit” of the bulk of the material is to discharge via pipe to the sea bottom at tidal extremes and minimising re-suspension requires cover with heavy material before inter-tidal currents become strong.
9.5. The Licence Holder must ensure that no material is deposited after 4th March 2016 without written confirmation from NRW, acting on behalf of the Licensing Authority, that they are satisfied the material is suitable for deposit at site LU110.
9.11. The Licence Holder must ensure that best practice is used to minimise re-suspension of sediment during these works.
---------------------------------------------------------------------------------------------------------
Data for U238 and Radium in 2009 samples taken at depth
3 out of the 5 samples were significantly higher at depth (up to 3x for Radium - Ra).  The NRW failure to require deep samples means only the 2009 data are representative of the bulk of the material to be dredged.  As there are so few data, the maximum plus a safety factor has to be adopted.  This raises CEFAS’s 5.8 μSv/yr calculated level, potentially to above the 10 μSv/yr limit.
Table B.15  Uranium-238 and Radium-226 concentrations for Vibro core samples  (also in [1] Appx B)
FUGRO survey of five locations in vicinity of intake, outfall and jetty, on 9/11 and 15/11 2009
Sample          U: surface/deep    Ra: surface/deep    depth           Date
1230/1231      48.73 / 46.13     25.25 / 27.65     4.35-4.42m      9/11
1232/1233      43.98 / 71.23     24.46 / 71.25     3.0-3.08m        9/11
1234/1235      39.46 / 41.25     22.43 / 30.30     4.7-4.8m          15/11
1236.1237      30.83 / 50.9       15.56 / 29.10     1.94-2.16m      15/11
1238/1239      50.65 / 68.56     25.29 / 73.57     3.0-4.12m        15/11

---------------------------------------------------------------------------------------------------------

Wednesday, 1 February 2017

Restart to our Webpage

WE are re-starting posting on this Webpage, to cover the many issues from Tidal Lagoons to Air Pollution.  
The incinerator campaign is covered primarily on the Facebook page: Stop the Barry Town Incinerator - where we have just won the NRW to accept full public consultation -  meeting at Castleland Community Centre 13th Feb.

Next meeting of Barry&Vale Friends of the Earth is 
              Tuesday  7th February, at 7-30 in the Castle Hotel, Jewel Street, Barry.

Several members attended the Aberthaw Power Station demonstration on Saturday, called by 'Reclaim the Power' to close down this highly polluting plant. We need Green Energy projects which make use of our tides, winds and the sun.
We are setting up air pollution (NO2) monitoring test tubes in Barry and the eastern Vale to expose the heaviest polluted areas.
At the latest LDP session, we put a strong case against the Cosmeston Green Field costal housing development.
We also appeared at the Five Mile Lane CPO Inquiry into converting this to a 60mph road through archaeological sites, SINCs and SSSI woodland.  This disrupts local farmers taking animals and equipment between fields. They include a much needed path/cycleway to the Hawking Centre, but refused to consider an alternative low-impact path from Waycock's Cross. 
The Group were pleased to see Councillors challenging the 'steamroller' of the Planning Department at their 5th January Planning Meeting, when the Northcliffe Lodge development (Penarth) and the United Reform Church development (Windsor Rd, Barry west end) were rejected.   We hope the Councillors will continue voting to protect the environment and rejecting crammed development. 
Note that the Planners struck back** after their defeat and tried to get a tight new "protocol" against Cllrs challenging their recommendations - but the non-Labour councillors combined to vote it down.

Keith Stockdale
Barry&Vale Friends of the Earth Coordinator

** AFTER NORTHCLIFF – THE VALE COUNCIL’S PLANNING EMPIRE STRIKES BACK

https://penarthnews.wordpress.com/2017/01/30/northcliff-lodge-defeat-has-changed-vale-planners-attitude-council-is-told/