FoE quoted the First Minister's letter of 29 Sept. to the Vale Council:
- A “precautionary approach should be taken” and “additional environmental considerations” should be included. It referred to Minerals Planning Policy Wales (MPPW) which specifies “an environmentally acceptable way” of operation and being “consistent with the principles of sustainable development” for unconventional gas development.
There was a lengthy exchange about a Condition to be set on noise levels if the application was permitted. The Inspector first proposed noise guidance levels used for opencast mining and quarrying. FoE said no - to use the policy for industrial areas close to homes, with non-disturbing night-time levels in accord with WHO guidance. The Vale officers failed to support FoE's approach, even though this was used at the Sunrise wood-burner inquiry. So the issue is left to the Inspector's decision. Whose side are the Vale officers on?